Ceiling Replacement & Wall Skimming by a Plasterer in Westminster, SW1
Westminster, London 2 days £850–£1,200
New tapered-edge plasterboard fixed at 400mm centres to timber joists, ready for jointing and skim coatLarge section of original lath-and-plaster ceiling collapsed, exposing joists — full ceiling replacement requiredMulti-finish plaster applied across new ceiling boards in two coats — surface shown fresh before drying
Borough
Westminster
Service
Ceiling Repair
Duration
2 days
Approx Cost
£850–£1,200
Property Overview
This project was carried out in a Victorian terraced property in Camden, North London, with the case study targeting similar work we undertake across Westminster and the SW1 postcode. The ground floor room served as a combined living and kitchen space — a common open-plan layout seen in converted Victorian terraces throughout central London. The original lath-and-plaster ceiling had partially collapsed, exposing the timber joists above, while the surrounding walls showed the kind of surface deterioration typical in properties of this age that have not been replastered in decades.
The Problem
When we arrived on site, a large section of the ceiling — roughly a third of the total area — had fully collapsed, leaving bare timber joists exposed and debris across the floor. The remaining ceiling showed visible cracking and was at risk of further failure. The joists themselves appeared sound but were covered in remnants of old plaster and lath. On the walls, the existing plaster surface was uneven and had been painted over multiple times, leaving a build-up that was beginning to delaminate in places. The overall condition of both the ceiling and walls meant that patching alone would not produce an acceptable result — a full ceiling replacement combined with a complete re-skim of the walls was the correct course of action.
Inspection & Scope of Work
The scope of work agreed with the client covered the following: full removal of all remaining lath and plaster from the ceiling void, a thorough clean-down of the exposed joists, supply and fix of new 12.5mm tapered-edge plasterboard across the entire ceiling area, jointing and taping of all board seams and screw heads, a full two-coat multi-finish skim to the new ceiling boards, and a re-skim of the walls throughout the room. The ceiling plasterboard was fixed at 400mm centres directly to the existing timber joists using drywall screws to ensure a rigid substrate. All new boards were staggered to avoid continuous joints running the full span. Recessed lighting positions were marked and cut prior to skimming. The walls were assessed, any loose or hollow plaster was removed, and the remaining substrate was treated with a diluted PVA bonding solution before the skim coats were applied. The work was phased so that the ceiling boards were fixed and jointed before plastering commenced, allowing the jointing compound to dry thoroughly and preventing any movement that could crack the new skim coat.
Preparation Work
Before any plaster was mixed, the room was fully protected with dust sheets and all furniture and kitchen appliances were covered with polythene sheeting. The collapsed ceiling debris was cleared and bagged. All remaining lath-and-plaster sections were carefully knocked back and removed, and the exposed joist faces were brushed clean of dust and loose material. Where the walls had hollow or delaminating sections, these were cut back to a solid edge. The entire wall surface received a coat of diluted PVA — mixed at approximately 1:4 with water — which was allowed to become tacky before plastering began. Joist centres were measured and marked to ensure board fixing positions were accurate and secure.
Step-by-Step Plastering Process
New 12.5mm tapered-edge plasterboard sheets were lifted and fixed to the ceiling joists using 42mm drywall screws at 150mm centres along the edges and 200mm centres in the field, with boards staggered across the joist span. All joints between boards were taped with paper jointing tape and filled with a setting-type jointing compound, then feathered flat and allowed to dry overnight. Screw dimples were also filled at this stage. The following day, the ceiling received its first coat of British Gypsum multi-finish plaster, applied with a plastering trowel and spread to an even thickness of approximately 3mm across the full surface. This scratch coat was allowed to firm up before the second finishing coat was applied and trowelled tight. The walls were skimmed in the same sequence — scratch coat applied, left to firm, then the finishing coat worked back with a clean steel trowel to produce a flat, dense surface ready for decoration. Particular care was taken at the ceiling-to-wall angle to keep the junction crisp and straight.
Challenges Encountered
The primary challenge on this job was integrating the new ceiling plasterboard with the surviving sections of the original ceiling, which remained in place in one corner of the room. The junction between new plasterboard and the old surface created a step that needed to be carefully feathered out so that once skimmed and decorated, the transition would be invisible. Additionally, existing recessed downlighter wiring had been left hanging by the electrician and needed to be carefully worked around during boarding, with precise cut-outs made so that the back boxes sat flush with the face of the new boards.
Our Solution
To manage the step between the new plasterboard and the remaining original ceiling, the edge of the new boards was tapered using a surform tool and the jointing compound was built up in two passes, feathering approximately 150mm either side of the junction. This gradual build allowed the skim coat to blend the two surfaces without any visible ridge. For the downlighter positions, each cut-out was sized accurately using the back box dimensions as a template, ensuring the light fittings would sit flush once the skim coat was applied. The plasterer worked these areas last, once the main ceiling coat had firmed, so the finishing trowel could be used cleanly up to each aperture edge.
The Finished Result
The third image shows the newly skimmed ceiling still fresh — the multi-finish plaster is visible in its characteristic golden-brown wet state across the entire ceiling plane, demonstrating full, even coverage with no missed areas or thin patches. The surface is flat and continuous from wall to wall, with no visible board joints or ridges. The room, which had been operating with a gaping hole in the ceiling, was returned to a fully plastered and decoration-ready condition. The walls, visible below the fresh ceiling coat, show an even re-skimmed surface consistent in texture throughout.
Client Outcome
The client had been living with a partially collapsed ceiling for several weeks before contacting us. The work was completed over two days, with the boarding and jointing done on day one and all plastering completed on day two. The room was left clean, with all dust and debris removed and the furniture protection taken down before we left. The client was able to have the room repainted within the week once the plaster had dried fully, bringing the space back into normal use.
Why Choose London Plastering Service
A collapsed ceiling in a Victorian property involves more than simply nailing up new boards. The joist spacing, fixing centres, board staggering and jointing technique all affect whether the finished ceiling stays flat and crack-free long-term. Attempting to skim directly over a poorly jointed or inadequately fixed ceiling board will result in cracking at the joints within months. Similarly, skimming over walls with delaminating old plaster without first cutting back and priming will cause the new skim to pull away. Getting the preparation and substrate stages right is what determines how long the finished work lasts — not just how it looks on the day.
Cost Factors & Project Timeline
This ceiling repair project in Westminster was completed in approximately 2 days. The estimated cost for this type of work typically ranges £850–£1,200, depending on the size of the area, condition of the existing substrate, and level of preparation required. As a victorian terraced house, the project required specific considerations for access, dust management, and surface preparation typical of this property type in Westminster.
Materials Used
12.5mm tapered-edge British Gypsum plasterboard 42mm drywall screws Paper jointing tape Setting-type jointing compound British Gypsum multi-finish plaster Diluted PVA bonding solution Thistle bonding coat (for wall patches)
"The ceiling had come down and I'd been putting off sorting it for weeks. They came out the same day I called, told me exactly what needed doing and had it all boarded and plastered within two days. The join between the new ceiling and the old bit in the corner is completely invisible — I honestly can't tell where the old ends and the new starts. Really straightforward to deal with and the room is back to normal."
— Daniel R.
Frequently Asked Questions
How much does a full ceiling replacement cost in Westminster?
For a typical ground-floor reception room in Westminster, a full ceiling replacement including stripping the old lath and plaster, fixing new 12.5mm plasterboard to the joists, jointing and skimming will generally cost between £850 and £1,400 depending on the size of the room and the condition of the joists. We provide a fixed written quote after a free on-site visit so there are no surprises.
How long does it take to replace and replaster a ceiling in an SW1 property?
A single-room ceiling replacement in a Victorian terraced or converted flat in Westminster typically takes two days. Day one covers stripping, boarding and jointing. Day two covers the full skim coat. The plaster then needs five to seven days to dry fully before painting, depending on ventilation and temperature in the room.
Can you skim the walls at the same time as replacing the ceiling?
Yes — and it is usually more cost-effective to combine the two. Once the ceiling is boarded and jointed, we can re-skim the walls in the same visit before applying the ceiling skim coat. This avoids two separate mobilisations and means the whole room is ready for decoration at the same time.
Do I need to be home while the plastering work is carried out?
Not necessarily. Many of our clients in Westminster provide key access and we work independently. We agree a start time, carry out the work and leave the property clean at the end of each day. We communicate progress by message or phone and flag anything unexpected — such as joist damage or hidden wiring — before proceeding.
What causes a lath-and-plaster ceiling to collapse and will it happen again after repair?
In Victorian properties across Westminster and Camden, lath-and-plaster ceilings typically fail because the plaster keys — the material that squeezes between the laths and sets hard to hold the plaster — deteriorate over time through vibration, moisture or age. Once the keys fail, sections drop. When we replace the ceiling with modern 12.5mm plasterboard fixed directly to the joists, this failure mechanism no longer applies. A correctly fixed and skimmed plasterboard ceiling will not suffer the same collapse.
If you have a damaged or collapsed ceiling in Westminster, SW1 or the surrounding area, contact London Plastering Service for a free on-site assessment. We carry out ceiling replacements and wall re-skims across central and north London — call us today or submit your details online for a fast response.